Wednesday, February 3, 2010

updates

hi all

any updates on the pumping stn power ,and if any units are going to connect to the 3 houses line?

regards
robert

3 comments:

  1. Had very quick word with Gary, who mentioned they have not quite cracked the pumps with RCD, but was going to do something tomorrow. Quartermain seem to still be doing quite a bit (mainly backfilling I guess)

    Know on Monday Chris left the trench behind the units until last minute in case any cables went in, but did fill them.

    There was a generator on for Ironing today. Think Gary said he spoke with Matt and if they do connect then SSE would not have to switch us off to do so - not sure if that means something is imminent or not.

    ReplyDelete
  2. thanks iain,do you mean the main genny? or a small genny running directly behind our houses ?

    ReplyDelete
  3. small gen behind the units, not so loud

    ReplyDelete